We Can Cut Nuclear Build Costs With AI | Jonathan Webb artwork

We Can Cut Nuclear Build Costs With AI | Jonathan Webb

MTS

October 24, 2026

The Nuclear Company CEO Jonathan Webb details Prosperity One, a proposed 6.6 GW nuclear campus in Lewis County, Kentucky. He explains how leveraging Westinghouse AP1000 reactors and Palantir's AI ontology could enable non-nuclear construction to begin in 2027 and reach full-bore deployment by 2028.

0:00

Jonathan Webb

What we really did was look at all the cost and schedule pieces and utilizing technology. I did the AIP con when we first announced working with Palantir, but building a nuclear ontology for deployment, I mean, it's going to be millions of data points from logistics, supply chain, and really our client is the frontline worker. And how do we get them real-time information and kind of deconstructing what happened at Vogel 3 and 4? You were looking at 10,000 people over 12 years to build the asset, working at maybe 15-20 percent labor efficiency. So even if we got that to 60 percent, which still is very low, right?

You're looking at a massive reduction in schedule, and as a result, a massive reduction in cost.

0:48

SPEAKER_2

Hello, everyone. Welcome back to MTS. Today, I am joined live with Jonathan Webb, the CEO of The Nuclear Company, which this morning announced Prosperity One. This is a proposed 6.6 gigawatt nuclear campus in Lewis County, Kentucky. Jonathan, welcome to MTS.

1:04

Jonathan Webb

Howdy.

1:05

SPEAKER_2

Howdy. Okay, I have to ask, where are you calling in from? What is the setup that we're seeing right now?

1:10

Jonathan Webb

Yeah, well, this is our beautiful campus of Prosperity One, about 4,000 acres on the Ohio River. So you got the Appalachian Mountains behind me, and you got the Ohio River that you can't see out in front of me.

1:23

SPEAKER_2

Wow, so I know this is just the start. What you guys announced today is just the very beginning. What's the big plan here?

1:31

Jonathan Webb

Well, the beginning has been for a couple of years. So a company is a little over three years old. We did start in Kentucky.

Large reason we started here was growing up in a coal state, seeing a lot of the coal plants shut down. We got a need for power in the region, and so we got to put more power on the grid. But beyond that, you might see up behind me, there's the 765 KV line. It's the largest transmission line in the country, and it connects us to PJM, which is the entire Northeast. Then the Ohio River has got about six times the amount of water we would need for the reactors we'd be building here. So this has been in the works for a couple of years. We've looked at about a dozen states, met with governors, and looked at about, I call it 1,500 properties. And today's the day that we've officially announced the project to the world, start working with the community, and go get this wonderful property under construction in the not-so-distant future.

2:29

SPEAKER_2

Wow. And so the not-so-distant future. I am curious though, what does the not-so-distant future mean? Like now that it's officially announced, the public all knows about it. What are we talking about when it comes to timelines here?

2:41

Jonathan Webb

Yeah. So one of the reasons we've been working with the owners of Westinghouse kind of before the Ap1000 got back in vogue a bit, which in the last kind of year and a half, the federal admins put a focus on it.

You can look at the recent kind of updates with the NRC.

We're excited about all the new reactors coming to market. Think there's going to be great advantages with many of them. You've had them on your show. But the benefit to the Ap1000 for us is, we want to deploy reactors, and we want to get gigawatts on the grid as quickly as possible, and being able to use the lessons learned, what we found, what went right, what didn't go right. This is a wonderful technology, a great machine. They got them up and running. 93 percent capacity factor, almost fastest, I think, than anywhere in the world, down in Georgia after they built them. So it had some cost challenges and schedule challenges on the build, but great asset to run. And so by utilizing the AP1000, we're going to be working the federal administration on a very prudent path to permitting a Greenfield property. And we're going to move it at the president's speed, where he's been able to lead on a lot. The last admin was leaning in to nuclear, obviously. Chris Wright and the president have made it clear that nuclear is a priority. So we're going to go in with a pretty solid plan and look forward to partnering with the Nuclear Regulatory Commission to get this property permitted. And my goal is to get dozers and men and women and crews on this construction site as soon as possible. I think realistically, we could have some non-nuclear construction going in 27 and kind of hit it full bore in 28

Read the other 11 minutes of this episode here.

$15 gets you this episode and 99 more. Credits never expire. After checkout, one link brings you back here to read it.

Not what you expected? Full refund within 14 days.

Thousands of transcripts fetched by people building searchable podcast archives

Fetch transcripts with code

The same credits work from a script or an AI agent. The demo key returns a sample episode in full, no card needed:

request
curl -H "x-api-key: pt_demo" \
  https://spoken.md/transcripts/1000651996090

Markdown with the speakers named, for your notes, your knowledge base, or anything that makes HTTP calls.

From $0.10 per transcript. No subscription. Credits never expire. Prices exclude VAT, added at checkout for EU customers. Not what you expected? Email us within 14 days with 20 or fewer credits used and we refund the pack in full.

Using your own key:

request
curl -H "x-api-key: YOUR_KEY" \
  https://spoken.md/transcripts/1000797921729